PARKER PERFORMING ARTS SCHOOL
New Construction
Parker, Colorado
Parker Performing Arts School broke ground on April 24th 2016 and was completed on September 23rd 2016. This 50,000SF performing arts school sat on 7 acres and was complete in 22 weeks. This project was finished without any non-owner initiated change orders and without compromises on scope or quality. This was achievable only because of our intensive preconstruction involvement and our singular focus on delivering on our commitments.
Project Stats
Total Contract Amount
50,000 SF New Construction
$10,390,819 MM
Completion Date
September, 2016